Wind Farms
Last updated at 11:27 on 05/01/2017
Full details and particulars of the information required are:
- Accounts and trading information:
- Copies of the audited accounts to include detailed profit and loss accounts for the most recent 3 years for which figures are available. (Certified accounts will suffice where audited accounts are not prepared
- Management accounts to cover period from date of last accounts up to current date.
- projections to cover the next 12 month period.
- Market information:
- A copy of the lease for properties / lands held on lease.
- Date of purchase and price paid, for freehold and leasehold properties / lands acquired over the past 5 years.
- Full details and costs of construction / development works carried out, to include a detailed breakdown of same.
- Layout plan for the wind farm.
- County Council planning reference number(s).
- Date(s) of construction and commission date(s)
- Details of wind turbine generators to include number, make, nominal output, etc
- Total Installed Generating Capacity (TIGC).
- Total annual production in Megawatt Hours for the past 5 years OR the estimated annual production for new developments
- Capacity factor.